ServMan’s Retainage Module should be used in conjunction with the Progressive Billing Module if you have large construction jobs that span a number of months or years until their completion.
Retainage is a portion of a project's price which is withheld until the work is complete. The concept of retainage provides an incentive to the contractor or subcontractor to complete the project as well as protects the owner against any liens, claims or defaults, which may surface as the project nears completion. The amount withheld from the contractor or subcontractor should be determined on a case-by-case basis, and is usually based upon such factors as past performance and the likelihood that the contractor or subcontractor will perform well under the contract.
There are two types of retainage; A/R retainage that your clients require of you and A/P retainage that you may require of your vendors. ServMan’s retainage module provides you with a solution for handling both. This section will explain the proper setup and use for both managing your retainage on billings to your clients (A/R Retainage) and tracking your retainage invoiced to and owed by you to your vendors (A/P Retainage).
After completing this session you should understand how to setup, manage, and monitor retainage in ServMan. Specific learning objectives include the following:
Purpose of Retainage
Back office ServMan must be at Version C.54 or later
Please have your ServMan project manager activate the following settings:
USE_RETAINAGE_AR=1
USE_RETAINAGE_AP=1
Setting must be placed in the each company file not the root.
The retainage receivable account is a subaccount within accounts receivable. It is a short-term asset account with a natural debit balance on the balance sheet. Under accrual accounting, a contractor posts a debit to the retainage receivable account when it fulfills the obligations tied to the retainage.
Enter the GL code
Select Accounts Receivable from the dropdown
Enter a description for this GL Code
No other information is necessary
• Select Utilities > Program Settings/ Defaults from Menu Bar
• A/R Settings tab
• Enter the A/R Retainage GL Code
• Enter the Default A/R Retainage % field
• Enter the Default Stored Materials Retainage % field
A/P Retainage may be set as a default at the vendor level, entered directly on a PO at creation, upon receipt of goods or directly on a bill received from the vendor. All retainage fields are editable at any stage of the process.
The retainage payable account is a subaccount within accounts payable.
Enter the GL code
Select Accounts Receivable from the dropdown
Enter a description for this GL Code
No other information is necessary
Setting up the retainage on a vendor will calculate the retainage amount on ALL bills received from the vendor.
On the Purchasing Default tab:
The Manage A/P Retainage screen displays all retainage history for the vendor, along with the current balance
Retainage can be set on any work order simply by entering a retained amount in the Retainage field at the bottom right corner of the Work Order Setup screen.
NOTE: This is NOT recommended by ServMan though the ability does exist.